There's been a recommendation that plans to build Norfolk's controversial waste incinerator should be scrapped.

View all 11 updates ›

The £30m bill for pulling Norfolk's incinerator plans

The cost to the people of Norfolk over the shock decision to pull out of plans to build a waste incinerator at King's Lynn, has been revealed.

Norfolk County Council will be forced to pay huge financial penalties as it prepares to officially scrap the project next week.

A series of Government delays in giving planning permission for the incinerator threatened to push the penalities for dropping the scheme, higher and higher, giving the council no other choice but to pull out.

Pulling out now leaves Norfolk County Council facing a bill of £30.26 million pounds. They have financial reserves of £19m and with an under spend this year of £3m, it leaves them with £8m still to find.

Click below to watch a report by ITV News Anglia's Natalie Gray