Work us beginning to repair storm damage to Whitehaven Harbour. The structure, part of which is an ancient monument, was badly damaged by huge waves and winds of up to 100 miles per hour in December.

Live updates

Advertisement

Repair works due to take several weeks

The Whitehaven Harbour Commissioners’ have worked for many years with the Environment Agency in order to protect the town from inundation from the sea within the harbour. Harbour Commissioners’ are delighted with the support and the speed at which the Environment Agency have provided the funding and the technical support. Works are due to start week commencing 3rd March and will be scheduled to finish late March early April."

– Celia MacKenzie, Whitehaven Harbours Commissioner

£324,000 funding secured for repair work

Copeland Borough Council, the Environment Agency and the Whitehaven Harbour Commissioners have secured £324,000 to repair storm damage to flood defences at Whitehaven Harbour.

On Thursday 5 December a severe storm coupled with one of the highest spring tides of the year caused unprecedented structural damage to the harbour and in particular to the Old Quay, which is a Scheduled Ancient Monument. Repairs to the structure are urgent as additional storms would create further damage to an already weakened structure, compromising the towns flood defence system.

“The money was secured from the £130 million emergency funding announced by the Government to aid the flood relief effort and repair damaged flood defences.”

– Craig Cowperthwaite, Environment Agency

£300,000 secured for harbour repairs

Work is under way to repair damage to Whitehaven Harbour.

The Environment Agency, Copeland Borough Council and the Whitehaven Harbour Commission has secured more than £300,000 for repairs.

Work is under way to repair damage to Whitehaven Harbour Credit: ITV News Border

Damaged stonework will be replaced and the structure strengthened to protect against future bad weather.

Maintenance work is also being carried out on the lock gates Credit: ITV News Border

Maintenance work is also being carried out on the lock gates.

Work begins to repair Whitehaven Harbour

Work is beginning to repair storm damage to Whitehaven Harbour.

Work is underway at Whitehaven Harbour Credit: ITV News Border

The structure, part of which is an ancient monument, was badly damaged by huge waves and winds of up to 100 miles per hour in December.